1959. Naoshima, Japan
Research began in 1959 to develop a new smelting
mechanism. Experiments were conducted at
the Naoshima Smelter using the then-existing
slag fuming furnace on "injection smelting",
which involved injecting the charge materials
and pressurized air into a molten bath.
These experiments showed that this new method
would enable rapid smelting of concentrates
with low-copper slag. A small-scale pilot
plant was then built at Naoshima for further
experiments. The test operation confirmed
the technical superiority of the new smelting
mechanism.
However, for the commercialization of a continuous process incorporating
this new smelting method, various technical problems such as the improvement
of the service life of the tuyeres and the transfer of intermediate products,
still remained to be solved.
1968. Onahama, Japan
A pilot plant, with a design capacity of 6,000 mtpy copper, was constructed
at the Onahama Smelter of Onahama Smelting & Refining Co., Ltd., a
subsidiary of Mitsubishi Metal Corporation (now Mitsubishi Materials Corporation).
In this pilot plant, top-blow lances were successfully used instead of
tuyeres. The pilot operation continued for two years and established the
basic design and operation parameters of the Mitsubishi Process.
1970. Onahama, Japan
As a preparatory step for future commercialization, a semi-commercial plant,
with a design capacity of 18,000 mtpy copper was built at Onahama.
Through the operation of this plant, the data necessary for the construction
of a commercial unit was accumulated, and a process control system was
developed.
1974. Naoshima, Japan
First commercial installation, with an original design capacity of 48,000
mtpy copper, utilizing the Mitsubishi Process was established.
By 1980, as a result of productivity improvements, including increased
solids feed, and the use of higher oxygen/air ratios for the S and C furnace
lance blowing, the plant capacity was lifted to 90,000 mtpy without any
change in furnace dimensions.
1981. Timmins, Canada
First Mitsubishi Process Licensee, Texasgulf
Canada, a subsidiary of Texasgulf Inc. (later
acquired by Falconbridge), established a
new continuous copper smelter at Timmins,
Ontario with an original design capacity
of 60,000 mtpy copper.
In 1983 Mitsubishi Materials provided a basic engineering package to increase
the Mitsubishi Process plant capacity at Timmins to over 90,000 mtpy copper,
utilizing higher oxygen enrichment.
Phased plant modifications and additions started at Timmins in 1984 and
were completed by mid 1986. At each stage, the anticipated increases in
blister production were achieved with no changes having to be made to furnace
dimensions.
The optimization of oxygen enrichment and other general improvements have
further improved the Mitsubishi Process plant capacity at Timmins to over
125,000 mtpy.
The plant was shutdown in 2010 due to the drain of copper mine.
1991. Naoshima, Japan
New Mitsubishi Process plant was established,
with a design capacity of 204,000 mtpy copper.
This new Mitsubishi Process plant has, as planned, successfully rationalized
Naoshima's copper operations by completely replacing the older conventional
(Reverb/P-S) smelter, the original Mitsubishi Process plant, and their
respective anode casting plants.
The capacity was increased to 270,000 mtpy of copper in 2003.
1997. Onsan, South Korea
Second Mitsubishi Process licensee, LG Metals
(Currently LG-Nikko) establishesd a new Mitsubishi
Process line in addition to their conventional
flash smelter + PS convertor line, to increase
total output. The Mitsubishi Process was
selected over other processes, first for
enviornmental considerations, and second
for production economy.
In addition to supplying proprietory equipment,
Mitsubishi also supplied LG with basic engineering
services, technical advisory services during
the detailed engineering and construction
phase, training and start-up assistance.
The designed production was acheived in 1998, and the
capacity reached to 270,000 mtpy copper in 2006.
To this day, Mitsubishi and LG-Nilkko share
a close working relationship.
1998. Gresik, Indonesia
Third overseas plant was built in Gresik,
Indonesia. The plant is run by a consortium
consisting of Mitsubishi Materials Corp.,
PT Freeport Indonesia, Mitsubishi Corp.,
and Nippon Mining, and has a design capacity
of 200,000 mtpy.
The Gresik smelter, being built on a greenfeild
site, incorporates many improvements in design
over Naoshima, including better overall layout.
This has led the smelter to be described
by Dr. Herbert H. Kellog, former professor
of Columbia Univerity, as "the finest
copper plant that I have seen." (from
the Journal of Metals, Vol.52, No.11, November
2000).
The smelter produced 214,000 mtpy of new anode in 2001,
and the capacity reached to 300,000 mtpy in 2009.
1999. Port Kembla, Australia
Mitsubishi Converting furnace (C-furnace)
technology was licensed to Port Kembla Copper
Pty., Ltd., and coupled with pre-existing
Noranda reactor. The Mitsubishi C-furnace
replaced existing Pierce-Smith convertors.
Although the first of its kind in this endevour,
it is hoped that more smelters around the
world will embrace Mitsubishi 's C-furnace
technology as a more environmentally sound
alternative to current Pierce-Smith Convertors.
The capacity was small, only 140,000 mtpy,
and the plant was shut down in 2003 due to
the economical reason.
2005. Dahej, India
Hindalco Birla Copper established a new Mitsubishi Process line with
a capacity of 250,000 mtpy copper, in addition to their conventional
flash smelter + PS converters line and Ausmelt smelter and converter line.
Mitsubishi supplied HBC with basic engineering services, propriety equipment
and training and start-up assistance. Technical advisory services have been
supplied up to now.
2007. Onahama, Japan
Stand - alone Mitsubishi S furnace was additionally installed to reverberatory furnaces and PS converters line for increasing the treatment capacity of copper concentrates and recycle materials. Copper concentrates are mainly treated at S furanace with the capacity of 200,000 mtpy copper.
* Comparison of Mitsubishi Process Smelters *
Smelter |
Owner |
Start |
Capacity in 2012 |
Notes |
---|---|---|---|---|
Naoshima (Japan) |
Mitsubishi Materials |
1991 | 270,000 TPY | Consolidation of old Reverb. and MI lines |
Kidd Creek (Canada) |
Xtrata | 1981 | (140,000 TPY) Shut down |
First overseas licensee |
Onsan (Korea) |
LS-Nikko Copper Inc. |
1998 | 270,000 TPY | Addition to existing Flash smelting line |
Gresik (Indonesiaj |
PT. Smelting | 1998 | 300,000 TPY | First copper smelter in Indonesia |
Port Kembla (Australia) |
Port kembla Copper |
2000 | (120,000 TPYj Shut down |
Replacement of PS Converters with C-f`ce |
Dahej (India) |
Hindalco Birla Copper |
2005 | 250,000 TPY | Addition to existing Flash smelting & Ausmelt lines |
Onahama (Japan) |
Onahama Smelter and Refinery |
2007 | 200,000 TPY | Installation of S-f`ce beside existing Reverb -PS line |