Return to Menu

ADVANTAGES OF THE MITSUBISHI PROCESS

1. Process Advantages


* Layout of the new Mitsubishi Process Plant and the now abolished conventional smelter at Naoshima *

Abolished Conventional Smelter (hatched) - 108,000 MT/Y -
1.Fluo-solid Roaster
2.Reverberatory Furnace
3.P-S Converter
4.Anode Furnace
5.Casting Wheel
6.Converter Slag Conveyor
7.Compressor House

New Mitsubishi Process Plant - 270,000 MT/Y -
A.Conc.Dryer
B.Storage Bin
C.Smelting Furnace
D.Slag Cleaning Furnace
E.Converting Furnace
F.Anode Furnace
G.Casting Wheel
H.Compressor House
I.Control Room

* Layout of Gresik plant whose capacity reached to 300,000 tpy copper in 2009. *



2. Cost Advantages

The following table provides an indexed comparison between the Mitsubishi Process and other processes which are combined with conventional P-S converters.
The figures are based on studies carried out by various international engineering companies and Mitsubishi Materials's own internal cost data. Taking the Mitsubishi Process to be 100, the table compares the average costs of different processes, and makes appropriate adjustments for batch converting, slag grinding and flotation, the treatment of fugitive emission and so on.

* Indexed Cost Comparison *

Mitsubishi Process Other Processes (Average)
Capital Cost (*1)

(Excluding Refinery Costs)

100

(100)

105 - 120

(106 - 122)
Operating Cost
Manpower(*2)
Fuel Oil(*2)
Coal(*2)
Oxygen(*2)
Maintenance(*2)
Purchased Power(*1)(*3)
Total Off Gas Vol.(*2)

100
100
100
100
100
100
100

130 - 140
90 - 130
100 - 120
80 - 90
120 - 130
90 - 110
120 - 200

*1 Including smelter, slag flotation plant, oxygen plant, acid plant,
fugitive gas treatment plant and refinery
*2 Smelter and slag flotation plant
*3 Purchased power = Actual consumption - Turbine generated power, using the
waste heat boiler steam

In the other continuous converters to treat solid matte, the matte melt should be granulated by a large amount of water, screened, crushed and mechanically transported, and for converting the solid matte should be dried or pelletized (adding water), and a large amount of additional energy (fuel and/or oxygen) is necessary. Furthermore, for treating refinery anode scrap and purchased scrap, the additional furnace and fuel would be necessary although the big converter aisle and overhead crane would be unnecessary. Accordingly, the construction and operating cost would be higher than the Mitsubishi process.

Return to Menu